Global 60+ Plant Capacity Balancing and Workload Re-Allocation
A multinational industrial equipment manufacturer operating 60+ production facilities across 4 continents, producing custom hydraulic pumps, valves, and heavy gearboxes.
Run on Niyojan · Production Planning

Primary manufacturing facilities in North America operated at 95% capacity overload while secondary plants in South America sat underutilized at 60% capacity.
Enterprise Plant Command Cockpit → Multi-Plant Order Allocation → Dynamic Capacity Balancing → Global Constraint Identification
18% overall increase in enterprise fleet capacity utilization across 60+ manufacturing plants.
The challenge
Primary manufacturing facilities in North America operated at 95% capacity overload while secondary plants in South America sat underutilized at 60% capacity.
Planners managed facility schedules in isolated spreadsheet silos, making cross-factory workload re-allocation slow and complex.
Overloaded plants incurred massive unplanned overtime costs while underutilized plants suffered idle labor overhead.
How our team solved it, with Niyojan
- 01
Enterprise Plant Command Cockpit
Niyojan unifies active order books, machine utilization rates, labor availability, and shipping logistics across all 60+ facilities into one live dashboard.
- 02
Multi-Plant Order Allocation
Niyojan weighs global machine capabilities, tooling availability, customer delivery windows, and freight costs to calculate optimal order placement.
- 03
Dynamic Capacity Balancing
Niyojan proposes moving standard product runs from overloaded North American plants to open capacity bays in South America.
- 04
Global Constraint Identification
Niyojan flags multi-plant bottlenecks, such as global shortages of heat-treatment furnace hours, before schedule commitments are released.
- 05
Planning Lead Approval
The global planning lead reviews the proposed allocations and approves the master schedule before Niyojan publishes it to local plant ERP systems.
The outcome
- Primary manufacturing facilities in North America operated at 95% capacity overload while secondary plants in South America sat underutilized at 60% capacity.
- Planners managed facility schedules in isolated spreadsheet silos, making cross-factory workload re-allocation slow and complex.
- Overloaded plants incurred massive unplanned overtime costs while underutilized plants suffered idle labor overhead.
- 18% overall increase in enterprise fleet capacity utilization across 60+ manufacturing plants.
- 75% reduction in unplanned overtime costs by balancing workload evenly across global facilities.
- Accelerated global master planning cycle time from 10 days to 2 hours.
Delivered for a client; the client name is withheld under NDA. References are available on request.
Capabilities used
Every accelerator is assembled from the same capability layer, so a workflow you adopt here shares its foundation with the rest of the portfolio.
Run on Niyojan
Watch Niyojan run, end to end, in a few minutes.

Multi-plant production planning at enterprise scale.
See the Niyojan acceleratorMore from Niyojan

Dynamic Resequencing Following Unplanned Primary Line Failure
A high-volume automotive stamping and welding plant producing body panels for 3 concurrent vehicle assembly platforms.
Read the use case
Setup Grouping and Changeover Minimization in Contract Electronics
A high-mix Contract Electronics Manufacturer (CEM) operating 12 Surface Mount Technology (SMT) lines producing PCBA boards for automotive and industrial IoT clients.
Read the use case
Order SLA Protection and Overtime Minimization During Demand Spikes
A commercial HVAC equipment manufacturer producing custom rooftop air handling units with high seasonal demand surges during pre-summer months.