Order SLA Protection and Overtime Minimization During Demand Spikes
A commercial HVAC equipment manufacturer producing custom rooftop air handling units with high seasonal demand surges during pre-summer months.
Run on Niyojan · Production Planning

A 45% seasonal surge in customer orders threatened contract delivery SLAs, risking heavy liquidated damage penalties.
Demand Surge Schedule Simulation → Targeted Bottleneck Overtime → Non-Bottleneck Shift Smoothing → Customer Priority Rules
100% on-time delivery maintained across pre-summer demand spike season with zero SLA penalty fines.
The challenge
A 45% seasonal surge in customer orders threatened contract delivery SLAs, risking heavy liquidated damage penalties.
Plant managers authorized uncoordinated weekend overtime across all departments, driving labor costs up by 35% without resolving specific assembly bottlenecks.
Planners could not determine which specific departments actually required overtime to protect delivery SLAs.
How our team solved it, with Niyojan
- 01
Demand Surge Schedule Simulation
Niyojan models incoming order volumes against finite plant capacity, identifying exact delivery SLA breach risks.
- 02
Targeted Bottleneck Overtime
Niyojan calculates the minimum overtime hours needed at bottleneck work centers such as coil brazing to preserve 100% of order SLAs.
- 03
Non-Bottleneck Shift Smoothing
Non-bottleneck departments such as sheet metal fabrication stay on standard shifts, removing unnecessary overtime spend.
- 04
Customer Priority Rules
Niyojan sequences orders by contract penalty severity and customer SLA windows.
- 05
Plant Director Approval
Plant directors compare the cost and SLA trade-offs of each overtime proposal and approve the overtime plan.
The outcome
- A 45% seasonal surge in customer orders threatened contract delivery SLAs, risking heavy liquidated damage penalties.
- Plant managers authorized uncoordinated weekend overtime across all departments, driving labor costs up by 35% without resolving specific assembly bottlenecks.
- Planners could not determine which specific departments actually required overtime to protect delivery SLAs.
- 100% on-time delivery maintained across pre-summer demand spike season with zero SLA penalty fines.
- 62% reduction in overtime labor spend by restricting overtime exclusively to identified bottleneck workstations.
- Preserved project gross margins while absorbing a 45% volume surge.
Delivered for a client; the client name is withheld under NDA. References are available on request.
Capabilities used
Every accelerator is assembled from the same capability layer, so a workflow you adopt here shares its foundation with the rest of the portfolio.
Run on Niyojan
Watch Niyojan run, end to end, in a few minutes.

Multi-plant production planning at enterprise scale.
See the Niyojan acceleratorMore from Niyojan

Global 60+ Plant Capacity Balancing and Workload Re-Allocation
A multinational industrial equipment manufacturer operating 60+ production facilities across 4 continents, producing custom hydraulic pumps, valves, and heavy gearboxes.
Read the use case
Dynamic Resequencing Following Unplanned Primary Line Failure
A high-volume automotive stamping and welding plant producing body panels for 3 concurrent vehicle assembly platforms.
Read the use case
Setup Grouping and Changeover Minimization in Contract Electronics
A high-mix Contract Electronics Manufacturer (CEM) operating 12 Surface Mount Technology (SMT) lines producing PCBA boards for automotive and industrial IoT clients.
Read the use caseBring us the version of this that you actually have.
Every engagement is fixed in scope and milestone-gated. The scoping conversation starts with your systems, not with a template.